Project Type: Energy
SCE Antelope-Pardee 500 kV Transmission Project EIR/EIS
Under contract to the CPUC, Aspen is currently preparing a joint EIR/EIS
for Southern California Edison's (SCE's) proposed Antelope-Pardee
Transmission Project to provide capacity to transmit power generated by
planned wind projects in the Tehachapi and Antelope Valley areas. To
accommodate this need, SCE is proposing to construct a new, 25.6-mile
500-kV single-circuit transmission line between SCE's existing Antelope
and Pardee substations in northern Los Angeles County, California. The
proposed 500-kV transmission line would replace an existing 66-kV line
that traverses the majority of the proposed route between the Antelope
Substation in Lancaster and the Pardee Substation in Santa Clarita,
including approximately 13 miles within the Angeles National Forest.
The proposed project would include electrical interconnections at the
existing Antelope and Pardee substations, as well as an expansion of
the Antelope Substation and relocation of several existing 66-kV
subtransmission lines in the vicinity of the Antelope Substation. The
proposed project route would be constructed within an existing right-of-way
(ROW) for 22.8 miles, of which 17.5 miles would be widened. Construction
of a new ROW would be required for 2.8 miles of the proposed project route.
Currently, transmission of wind power from the Tehachapi and Antelope Valley
areas is constrained by the existing Antelope-Mesa 220-kV transmission line,
which would be overloaded by the addition of new wind generation. SCE
estimates that the proposed Project would increase overall system capability
to allow up to 350 MW of new wind generation to be interconnected with the
SCE transmission grid without overloading the Antelope-Mesa 220-kV line. It
would accomplish this by providing capacity to transmit power from the
Antelope Substation to the Pardee Substation rather than directing more power
to the Antelope-Mesa line. The proposed Antelope-Pardee project is needed
now to accommodate several wind generation projects that either have
applications pending before Kern County or are in the advanced planning
stage and expected to submit applications in the near future. Due to their
locations, these upcoming wind generation projects will need to interconnect
to the Antelope Substation to allow power to be delivered to load in the Los
Angeles area. However, these wind generation projects cannot be
interconnected to the SCE transmission system without an increase in
transmission capacity south of Antelope Substation. The proposed project will
allow these initial wind generation projects to interconnect to the
transmission system and allow time for future transmission upgrades to be
planned and constructed to accommodate more wind generation in the future.
The EIR/EIS will analyze eight alternatives, including an alternative that
avoids Forest System lands and an alternative that would involve installation
of a portion of the transmission underground. The alternatives that traverse
Forest System lands have been designed to reduce the visual impacts of the
transmission and minimize effects on other Forest resources. The alternatives
were selected based on an extensive alternatives screening process in which
a wide range of alternative routes, system configurations, tower types, and
underground technologies were evaluated.
On June 24, 2005, the CPUC issued a Notice of Preparation for the EIR for
the project and the Forest Service published a Notice of Intent to prepare
an EIS. Public scoping meetings were conducted in July 2005. The Draft
EIR/EIS is expected to be published in July 2006.
|