Project Type: Energy
PG&E Jefferson-Martin 230 kV Transmission Project EIR
Draft and Final EIRs were completed in 2003 for this highly controversial
27 mile transmission project. The EIR included a detailed Alternatives
Screening Report of over 200 pages, and the Final EIR includes the over
800 pages of comments on the Draft EIR, and responses to those comments.
Major issues included land use, biological resources, visual resources,
and EMF concerns. Aspen was awarded the Association of Environmental
Professional's Statewide EIR Award for the Jefferson-Martin 230 kV
Transmission Line Project Final EIR.
|